Free cookie consent management tool by TermsFeed

Pool-type Sodium-Cooled Fast Reactor (SFR).

Sodium-cooled fast reactor combining advanced engineering, passive safety, and manufacturing-first design, to build India’s most affordable modular reactor.

Utilising the natural properties of liquid sodium.

Sodium stays liquid up to 883°C, conducts heat exceptionally well, and preserves the fast neutron spectrum. As a direct consequence, the reactor runs at near-atmospheric pressure, eliminating the requirement for heavy pressure vessels and high-pressure containments.

Simpler to build and safer to operate by design.

ATLAS-150

Bharat Atomic’s ATLAS-150 will produce 150 MW of electricity.

[01/07]

Fully metallic

A fuel pin consists of metallic U-10Zr fuel in HT-9 steel cladding, with sodium filling the gap between fuel and cladding. Sodium coolant flows upward through the pins, collecting heat as it goes. The core is loaded once at commissioning and runs for twenty years without refuelling.

Compact pool-type vessel

The heated sodium, now at 510°C, rises into the hot pool inside a single sealed 5x5m vessel installed below grade. The core, the pumps, and all six heat exchangers sit inside this one structure with no external pipe connections.

Intermediate heat exchangers

Shell-and-tube exchangers across independent loops transfer heat from radioactive primary sodium to clean secondary sodium across a tube wall. Radioactivity stays on the primary side.

Primary pumps

Centrifugal pumps in the cold pool push cooled sodium back into the core, maintaining forced circulation during normal operation. Sodium's high thermal inertia means that even if flow is interrupted, the large pool absorbs heat gradually, buying time before temperatures approach safety limits.

Decay heat removal system

The pool is the first line of defence. The sheer thermal mass of the primary sodium absorbs decay heat and rejects it passively, buying not minutes but days. Dedicated loops then carry remaining decay heat through heat exchangers outside the building, transferring it to open air. Each loop is independently sufficient, without the need for pumps, power or operator.

Steam generators

Secondary sodium travels to the steam generators outside the vessel, producing superheated steam at 440°C. A conventional turbine-generator delivers 150 MW of electricity. The remaining thermal output can be delivered as process heat to co-located industrial users.

Safe shutdown mechanism

Control rods with boron carbide absorber fall into the core by gravity when power is cut. Safety rods form a separate, mechanically diverse system inserted by spring and gravity under any off-normal condition. Two entirely different mechanisms ensure a single failure cannot disable both simultaneously.

A multipurpose energy source, equipped to meet every demand Bharat could possibly have.

Targeting 150 MWe of firm, clean, and always-on power. Multiple units share site infrastructure, with twin-unit and four-unit configurations in development, reducing cost as capacity scales.

[01]

Always-on power for data centres, hyperscalers, and AI infrastructure

[02]

Baseload electricity for grids, remote communities, and even isolated areas

[03]

Process heat and steam at up to 440°C to co-located industrial facilities

[04]

Clean hydrogen through high-temperature electrolysis

Demo by 2029

completed

2026

Core neutronics and thermal-hydraulic codes and modelling

Q2 of 2026

Conceptual Reactor Design (CDR)

Q2 of 2026

Build initial reactor design engineering team

Q3 OF 2026

Pre-licensing regulatory engagement with AERB and DAE

Q3 OF 2026

NEEV (Nuclear Engineering & Experiment Validation) center facility setup (Pune)

Q4 of 2026

2027

Basic Reactor Design (BDR) freeze & detailed engineering design commenced

Q1 OF 2027

Reactor design testing in NEEV pilot facility & government facilities

Q2 OF 2027

Preliminary Safety Analysis Report (PSAR) initiated

Q3 OF 2027

Testing full-scale 1:1 non nuclear prototype reactor

Q3 OF 2027

Fuel load and first criticality achievement

Q4 OF 2027

2028

Licensing package submitted; AERB consent for siting & construction

Q1 OF 2028

Deployment activity begins in a partner's AI data center site

Q2 OF 2028

2029

Complete our Full scale 1:1 nuclear demo reactor i.e. ATLAS-150

Q2 OF 2029

2030

Mass production begins

Q2 OF 2030

2031

First unit enters commercial operation

2032

Scaling up production (NOAK)

Q4 OF 2032

2033

Towards a resilient future, together.

Collaborations & partnership.

Bharat's energy future is being built now. We are making decisions today that will echo for decades. The organisations collaborating with us would have shaped something that outlasts all of us. Join and build it with us.

Join the team.

We are building something that will exist long after all of us. A small number of exceptional people will be able to say they built it. If your work speaks for itself, you move fast, and you care about what this means for Bharat (India), come pitch what you bring to the table.

This is some text inside of a div block.